Approved Document L: Part L energy rules for extensions and homes

Approved Document L is the guidance on Part L of the building regulations, the conservation of fuel and power. For a London homeowner it decides how well an extension, a loft conversion or new windows must be insulated, and how much glass an extension can have before the designer has to prove the energy use by calculation.

Building regs L: what Part L covers

Part L sets energy standards for new buildings and for work on existing ones. Approved Document L comes in two volumes: Volume 1 for dwellings and Volume 2 for buildings other than dwellings. The edition in use is the 2021 edition incorporating 2023 amendments; the 2021 edition took effect on 15 June 2022, which is why people still search for Part L 2022 or the new building regs 2022. New 2026 editions of Approved Documents L (renamed Energy and Greenhouse Gas Emissions) and F were published on 24 March 2026 and apply from 24 March 2027, subject to transitional provisions; they mainly raise the standards for new homes, so check the edition that applies when your work is notified. You will also see the older names L1A, L1B, L2A and L2B: they were the four separate documents before 2021, for new dwellings, existing dwellings, new non-dwellings and existing non-dwellings.

U-values for an extension or loft conversion

A U-value measures how much heat passes through a wall, roof, floor or window: the lower the number, the better the insulation. For new elements in an existing house, including an extension, Table 4.2 of Volume 1 sets these limits, in W/m²K:

  • Roof, pitched or flat: 0.15
  • Wall: 0.18
  • Floor: 0.18
  • Windows: 1.4, or Window Energy Rating band B
  • Rooflights: 2.2
  • Doors with more than 60 per cent glazing: 1.4, or Doorset Energy Rating band C

In practice a warm flat roof needs a thick layer of PIR insulation board, a pitched roof has insulation between and under the rafters, and a solid floor has insulation over or under the slab. The designer or the insulation maker calculates the U-value for the build-up you choose.

Closer rear view of the dormer, KRAMAN Ltd, LondonExposed timber ceiling joists and brickwork during the Brockley house renovation, KRAMAN Ltd, LondonRear garden after landscaping: lawn, curved paving, a low dividing wall and a timber shed, KRAMAN Ltd, LondonTimber vanity unit with two countertop basins during fitting, KRAMAN Ltd, London

The 25 per cent glazing rule for extensions

The simple route for an extension limits the total area of windows, roof windows, rooflights and doors to 25 per cent of the extension floor area, plus the area of any existing windows and doors that the extension covers or removes. Many London kitchen extensions have more glass than that, with sliding doors and a roof lantern. Then the designer shows by calculation, often with SAP, that the house with the extension uses no more energy than it would with a compliant extension, usually by insulating better elsewhere.

Replacement windows, renovations and new boilers

Replacement windows must meet the same 1.4 U-value or band B; a FENSA or other registered installer certifies them. When you renovate an existing wall, floor or roof, for example by re-roofing or re-rendering a whole external wall, Part L can require you to upgrade its insulation: Table 4.3 sets a threshold, such as 0.35 W/m²K for a roof, below which the element is improved, to 0.16 for a roof, where that is technically, functionally and economically feasible. New heating systems, hot water and fixed lighting have their own minimum standards in the approved document.

Inside the Leytonstone garden outbuilding after plastering and painting, KRAMAN Ltd, LondonTimber rafters forming the hipped roof of the Highgate extension during construction, KRAMAN Ltd, LondonChimney stack on a tiled roof in Stratford during repair, under scaffolding, KRAMAN Ltd, LondonSlatted MDF panel finished in brown beside a sofa, KRAMAN Ltd, London

How we meet Part L on site

On our loft conversions and extensions the designer specifies the insulation build-up and building control checks it at the inspections. Keep the product data sheets and photographs of the insulation before it is covered: they answer the questions a buyer’s surveyor asks later.

Questions people ask

What does building control Part L check on an extension?

The insulation of the new walls, roof and floor, the windows and doors, the glazing area or the calculation that justifies more glass, and any new heating or lighting.

What is Approved Document L?

The government guidance on Part L of the Building Regulations 2010, conservation of fuel and power: Volume 1 for dwellings and Volume 2 for other buildings, in the 2021 edition incorporating 2023 amendments.

What U-value does an extension wall need?

A new wall in an existing dwelling, including an extension, has a limiting U-value of 0.18 W/m²K under Table 4.2 of Approved Document L Volume 1.

How much glazing can an extension have under Part L?

On the simple route, windows, rooflights and doors up to 25 per cent of the extension floor area plus the area of openings the extension covers; more needs a calculation such as SAP.

When did the new Part L come in?

The 2021 edition took effect in England on 15 June 2022, with transitional rules for work already notified; it has since been amended in 2023.

What were L1A, L1B, L2A and L2B?

The four volumes of Approved Document L before 2021: new dwellings, existing dwellings, new buildings other than dwellings and existing buildings other than dwellings.