Two storey extension cost in London: what sets the price, planning and build time

A two storey extension adds a bedroom or a bathroom upstairs as well as a bigger kitchen or living room below. In London it is one of the best ways to add space to a semi-detached or end-of-terrace house, and its foundations and roof serve both floors. Here is what sets the two storey extension cost, and what planning and building it takes.

How one set of foundations and one roof serve two floors

The foundations, the roof and the junction with the house are large parts of any extension. A two storey extension builds one set of foundations and one roof over two floors of space, so those parts serve twice the floor area of a single storey extension on the same footprint. The total is higher, because there is more to build, fit out and finish.

What sets the two storey extension cost

  • Size and shape: rear, side or wrap-around, and whether the upper floor covers the whole ground floor.
  • Structure: steel beams where the new rooms open into the house, and foundations for London clay and nearby trees.
  • The roof: a pitched roof matched to the house, or a flat roof where planning allows.
  • Upstairs connection: new openings in the back wall, a moved landing or a longer stair.
  • Fit-out: a bathroom or ensuite upstairs, a kitchen below, glazing and the finish of every room.
  • Fees: drawings, structural calculations, planning or a Lawful Development Certificate, building control and party wall surveyors.

Our house extension cost questions cover the single storey side, and our house extension page lists what goes into a quote.

Closer rear view of the dormer, KRAMAN Ltd, LondonTimber rafters forming the hipped roof of the Highgate extension during construction, KRAMAN Ltd, LondonChimney stack on a tiled roof in Stratford during repair, under scaffolding, KRAMAN Ltd, LondonTimber joists and insulation during roof work on the Walthamstow house, KRAMAN Ltd, London

Building a 2 storey extension: planning permission

A two storey rear extension can be permitted development on a house, within limits: it can extend no more than 3 metres beyond the rear wall, must be at least 7 metres from the rear boundary, the roof pitch must match the house as far as practicable, and upper-floor windows in a side wall must be obscure glazed and non-opening below 1.7 metres. Side extensions of more than one storey are not permitted development and need planning permission, as do extensions in a conservation area or on a house that has lost its rights. Our extension planning guide sets out the limits and the 45 degree rule councils use for neighbours’ light.

Cost of a two storey rear extension against a loft conversion

If the aim is one more bedroom, a loft conversion usually adds it with less structure and no loss of garden. A two storey rear extension adds space on both floors at once, which suits a family that also needs a bigger kitchen. On some houses both are built together, as on our Leytonstone project, which combined a rear dormer with a kitchen extension.

How long a double storey extension takes

On site, a double storey extension usually takes 16 to 22 weeks, after the drawings, planning or a Lawful Development Certificate, party wall notices and building control approval. A wall built on the boundary or excavation near a neighbour’s foundations needs notice under the Party Wall etc. Act 1996, and the notice period comes before work starts.

Questions people ask

How much does a two storey extension cost in London?

It depends on the size, the structure, the roof, the fit-out and the fees; we price each one from a site visit and the drawings, and do not publish an average.

Do I need planning permission for a two storey extension?

A two storey rear extension can be permitted development within the 3 metre depth and 7 metre boundary limits; side extensions of more than one storey need planning permission.

How long does a two storey extension take to build?

Usually 16 to 22 weeks on site, after the drawings, approvals and party wall notices.