A full rewire has two stages. First fix: the electrician lifts floorboards, cuts channels (chases) in the plaster and runs new cables to every socket, switch, light and fixed appliance, and to a new consumer unit. Second fix, after plastering: sockets, switches, lights and the consumer unit are connected, then the whole installation is tested. Smoke and heat alarms, an outside socket and wiring for a cooker, shower or garden office are planned at the same time. A partial rewire replaces only some circuits, for example a kitchen rewire when the kitchen is refitted.