# Two storey extension cost in London: what sets the price, planning and build time

Source: https://kraman.co.uk/blog/two-storey-extension-cost/
Updated: 25 November 2026

A two storey extension adds a bedroom or a bathroom upstairs as well as a bigger kitchen or living room below. In London it is one of the best ways to add space to a semi-detached or end-of-terrace house, and its foundations and roof serve both floors. Here is what sets the two storey extension cost, and what planning and building it takes.

[Alex Anokhin, KRAMAN Ltd](https://kraman.co.uk/about/). Published 25 November 2026.

## How one set of foundations and one roof serve two floors

The foundations, the roof and the junction with the house are large parts of any extension. A two storey extension builds one set of foundations and one roof over two floors of space, so those parts serve twice the floor area of a single storey extension on the same footprint. The total is higher, because there is more to build, fit out and finish.

## What sets the two storey extension cost

- Size and shape: rear, side or wrap-around, and whether the upper floor covers the whole ground floor.
- Structure: steel beams where the new rooms open into the house, and foundations for London clay and nearby trees.
- The roof: a pitched roof matched to the house, or a flat roof where planning allows.
- Upstairs connection: new openings in the back wall, a moved landing or a longer stair.
- Fit-out: a bathroom or ensuite upstairs, a kitchen below, glazing and the finish of every room.
- Fees: drawings, structural calculations, planning or a Lawful Development Certificate, building control and party wall surveyors.

Our [house extension cost questions](https://kraman.co.uk/blog/house-extension-cost-questions/) cover the single storey side, and our [house extension page](https://kraman.co.uk/services/house-extension-london/) lists what goes into a quote.

## Building a 2 storey extension: planning permission

A two storey rear extension can be permitted development on a house, within limits: it can extend no more than 3 metres beyond the rear wall, must be at least 7 metres from the rear boundary, the roof pitch must match the house as far as practicable, and upper-floor windows in a side wall must be obscure glazed and non-opening below 1.7 metres. Side extensions of more than one storey are not permitted development and need planning permission, as do extensions in a conservation area or on a house that has lost its rights. Our [extension planning guide](https://kraman.co.uk/guides/extension-planning-permission/) sets out the limits and the 45 degree rule councils use for neighbours’ light.

## Cost of a two storey rear extension against a loft conversion

If the aim is one more bedroom, a [loft conversion](https://kraman.co.uk/services/loft-conversion-london/) usually adds it with less structure and no loss of garden. A two storey rear extension adds space on both floors at once, which suits a family that also needs a bigger kitchen. On some houses both are built together, as on our [Leytonstone project](https://kraman.co.uk/project/leytonstone-5/), which combined a rear dormer with a kitchen extension.

## How long a double storey extension takes

On site, a double storey extension usually takes 16 to 22 weeks, after the drawings, planning or a Lawful Development Certificate, party wall notices and building control approval. A wall built on the boundary or excavation near a neighbour’s foundations needs notice under the Party Wall etc. Act 1996, and the notice period comes before work starts.

## Questions people ask

### How much does a two storey extension cost in London?

It depends on the size, the structure, the roof, the fit-out and the fees; we price each one from a site visit and the drawings, and do not publish an average.

### Do I need planning permission for a two storey extension?

A two storey rear extension can be permitted development within the 3 metre depth and 7 metre boundary limits; side extensions of more than one storey need planning permission.

### How long does a two storey extension take to build?

Usually 16 to 22 weeks on site, after the drawings, approvals and party wall notices.

## Read next

### [House extension costs in London: answers to common questions](https://kraman.co.uk/blog/house-extension-cost-questions/)

What sets the cost of a house extension in London: single or two storey, side return, over a garage, porch or garden room, and planning.

### [Permitted development extension rules: sizes, planning permission and the 45 degree rule](https://kraman.co.uk/guides/extension-planning-permission/)

Permitted development rules for rear, side and two storey extensions: sizes, prior approval, when you need planning permission and enforcement.

### [Party wall surveyor cost: who pays, agreed surveyors and the RICS](https://kraman.co.uk/blog/party-wall-surveyor-cost/)

What a party wall surveyor costs and who pays: one agreed surveyor or two, the third surveyor, schedules of condition and the RICS.

Sources: [GOV.UK: permitted development rights for householders, technical guidance](https://www.gov.uk/government/publications/permitted-development-rights-for-householders-technical-guidance) · [Planning Portal: extensions](https://www.planningportal.co.uk/permission/common-projects/extensions) · [GOV.UK: party walls and building work](https://www.gov.uk/party-walls-building-works).